Salzburg Airport, renovation of runway 15/33 and taxiways
Service road New Entry System
New construction of a connecting and access road from the eastern apron areas to the new New Entry Systems hall (non Schengen area) for buses
Project share: general planning LPH 1 – 6, planning services road construction, drainage
Lightning Exit 4 Taxyway Delta
Extension of the lighting of taxiway Delta, EXIT 4
Project share:
General planning LPH 1 – 6, planning service cable civil engineering, electrical engineering
Rehabilitation Runway 15/33
The general renovation of the concrete runway from 1959/60 was carried out by means of an asphalt superstructure above the existing surface.
The preliminary measures were carried out in 2018 during the non-operational nighttime period. The renovation work for the runway itself was carried out during a total closure of one week in 2019.